T1  - Review of a Possibility to use Bulldozers at Vostochno-Bernikovskiy Deposit
AU - Nikolaevich Ligotsky, Dmitry 
JO  - Journal of Engineering and Applied Sciences
VL  - 14
IS  - 17
SP  - 6460
EP  - 6464
PY  - 2019
DA  - 2001/08/19
SN  - 1816-949x
DO  - jeasci.2019.6460.6464
UR  - https://makhillpublications.co/view-article.php?doi=jeasci.2019.6460.6464
KW  - performance
KW  -rock material
KW  -ripper
KW  -Bulldozer
KW  -seismic velocity
KW  -layer-by-layer excavation
AB  - The open pit capacity has been increasing over the last year, thus, creating favourable conditions
to apply modern mining and hauling equipment and to adopt new advanced mining processes at
Vostochno-Bernikovskiy deposit. The open pit operations are equipped with a large fleet of different
equipment, however, the basic technical and economic performance indicators (productivity, profitability of
mining company and others) are not improving at sufficient rate. The study contains the research data for the
dependence of bulldozer performance on the average mucking distance and seismic velocity, adjustment factor
for surface slope (downward or upward) as well as an assessment of the rock breaking characteristics by the
seismic wave speed using a single-shank or multi-shank adjustable parallelogram ripper and a bulldozer with
a capacity of 634 kW and weight 104.5 t. These results allow development of non-explosive mining technologies
for construction materials as well as improving technical and economic performance of the open pit.